Question 1
The hospital's procurement policy requires at least three competitive bids for subcontracts above $50,000. The construction manager wants to award a $180,000 subcontract without bidding to a preferred subcontractor. What is the MOST appropriate action?
A. Split the work into four subcontracts of less than $50,000 each so that competitive bidding is not required
B. Follow the owner's policy: get competitive bids or a documented, approved sole-source justification
C. Award the subcontract, because the CM is solely responsible for selecting its subcontractors
D. Award the subcontract now and inform the owner of the decision at project close-out
Answer: B
Answer B. Follow the owner's policy: get competitive bids or a documented, approved sole-source justification WHY THIS IS THE BEST ANSWER Coordinating contractor procurement with organizational policies is a CHC outline task. Hospitals, especially nonprofit and public ones, have procurement and conflict-of-interest policies to ensure fair pricing and accountability. Sole-source awards require documented justification and approval. WHY THE OTHER OPTIONS ARE LESS APPROPRIATE
A. Splitting contracts to avoid bidding thresholds violates the intent of the policy.
C. The CM must follow the procurement policies required by its contract with the owner.
D. Late notification does not comply with the policy.
Question 2
Three bids are received for a renovation. Bid A: $1,200,000, excluding ICRA barriers (estimated at $85,000) and after-hours shutdown premiums (estimated at $40,000). Bid B: $1,310,000, including all scope. Bid C: $1,255,000, excluding ICRA barriers (estimated at $85,000). After leveling for scope, which bid is the lowest?
A. Bid B at $1,310,000
B. Bid A at $1,200,000
C. Bid A and Bid C are tied
D. Bid C at $1,255,000
Answer: A
Answer A. Bid B at $1,310,000 WHY THIS IS THE BEST ANSWER Bid leveling adjusts each bid for excluded scope so they can be compared on an equal basis. Leveled totals: A = $1,325,000; B = $1,310,000; C = $1,340,000. Bid B is lowest. Healthcare-specific items such as ICRA barriers and after-hours shutdown work are frequently excluded and must be checked. WHY THE OTHER OPTIONS ARE LESS APPROPRIATE
B. Leveled, Bid A is $1,200,000 + $85,000 + $40,000 = $1,325,000.
C. Leveled totals are $1,325,000 and $1,340,000, not tied.
D. Leveled, Bid C is $1,255,000 + $85,000 = $1,340,000.
Question 3
A hospital will buy imaging equipment through its group purchasing organization (GPO) contract and have the contractor install it (owner-furnished, contractor-installed). Which consideration is MOST important for the procurement plan?
A. Responsibilities can be decided when the equipment arrives at the hospital's loading dock
B. The contractor should solicit a different vendor to obtain better pricing than the GPO contract
C. The contractor should add its standard markup to the equipment cost because it is responsible for installation
D. Clearly define responsibilities for delivery, receiving, storage, rigging, installation, and coordination
Answer: D
Answer D. Clearly define responsibilities for delivery, receiving, storage, rigging, installation, and coordination WHY THIS IS THE BEST ANSWER OFCI procurement can save money through GPO pricing but creates interfaces between the vendor and contractor. A responsibility matrix covering delivery dates, receiving, storage, rigging, utility connections, installation, and testing prevents gaps and disputes. WHY THE OTHER OPTIONS ARE LESS APPROPRIATE
A. Late decisions cause delays, damage, and disputes.
B. The owner has already chosen GPO procurement.
C. Owner-furnished equipment is typically not marked up by the contractor.
Question 4
To meet the budget, the team proposes eliminating a redundant chiller from a central plant serving surgical and critical care areas, saving $400,000. What is the MOST appropriate response?
A. Evaluate the reliability impact on critical spaces, including failure scenarios, before deciding
B. Accept the proposal, because a $400,000 saving is significant for the project budget
C. Reject the proposal without further analysis, because all redundancy in a hospital central plant is required by code
D. Accept the proposal and plan to rent a temporary chiller if one of the units fails
Answer: A
Answer A. Evaluate the reliability impact on critical spaces, including failure scenarios, before deciding WHY THIS IS THE BEST ANSWER Value analysis must consider reliability, risk, and operational impact, not just first cost. Loss of cooling in ORs and ICUs can stop procedures and endanger patients. The team should evaluate N+1 needs, maintenance scenarios, consequences of failure, and the owner's requirements, possibly considering alternatives such as provisions for temporary chiller connections. WHY THE OTHER OPTIONS ARE LESS APPROPRIATE
B. Savings must be weighed against the risk of losing cooling to critical areas.
C. Some redundancy is a project requirement rather than a code mandate; analysis is needed.
D. Rental equipment may not be available quickly enough to protect critical areas.
Question 5
Two roofing systems are being compared: System A has a 20-year service life, and System B has a 30-year service life. What is the MOST appropriate way to compare their life-cycle costs?
A. Divide each first cost by its service life and pick the lower annual figure, without discounting
B. Compare annual maintenance costs only, since these represent most of the life-cycle cost
C. Use a common study period, including replacements and residual values in present value
D. Compare first costs only, since both systems will be maintained by the hospital's staff
Answer: C
Answer C. Use a common study period, including replacements and residual values in present value WHY THIS IS THE BEST ANSWER Life-cycle cost comparisons of alternatives with different service lives require a common study period. Replacement costs within the period and residual value at the end are converted to present value. This approach, described in ASTM E917 and NIST Handbook 135, gives a fair comparison. WHY THE OTHER OPTIONS ARE LESS APPROPRIATE
A. This simplified approach ignores discounting and residual value.
B. This ignores first costs and replacement.
D. First cost ignores differences in replacement timing and maintenance.
Question 6
For a 40-room patient tower addition, the team considers prefabricated bathroom pods and headwall assemblies. Which benefit is MOST relevant to constructability and financial stewardship?
A. Off-site fabrication can improve quality and cut on-site labor, duration, and disruption
B. Prefabricated assemblies eliminate the need for AHJ and owner inspections of the work
C. Prefabrication always costs less than conventional construction on a first-cost basis
D. Prefabrication removes the need for coordination among the design disciplines and trades
Answer: A
Answer A. Off-site fabrication can improve quality and cut on-site labor, duration, and disruption WHY THIS IS THE BEST ANSWER Prefabrication moves repetitive work into a controlled environment, improving quality, safety, and schedule, and reducing on-site activity, noise, and dust near occupied areas. It requires early design decisions and coordination. Financial benefits often come from reduced schedule and earlier revenue. WHY THE OTHER OPTIONS ARE LESS APPROPRIATE
B. Prefabricated components still require inspections and approvals.
C. First cost may be higher; benefits often come from schedule and quality.
D. Prefabrication requires earlier and more detailed coordination.
Question 7
At the schematic design stage, the owner asks why the cost estimate includes a large design contingency. What is the BEST explanation?
A. The contingency will be paid to the contractor at the end regardless of actual need
B. Contingency is included mainly to protect the estimator from criticism if bid prices come in high
C. Early estimates rest on incomplete design, so contingency covers scope that will emerge
D. A design contingency of this size is required by NFPA 101 for all hospital projects
Answer: C
Answer C. Early estimates rest on incomplete design, so contingency covers scope that will emerge WHY THIS IS THE BEST ANSWER Estimate accuracy improves as design progresses. Schematic estimates have wider uncertainty, so a design contingency is included and reduced in later phases. Understanding this helps owners set realistic budgets and avoid surprises. WHY THE OTHER OPTIONS ARE LESS APPROPRIATE
A. Design contingency is reduced as the design becomes more complete.
B. The contingency reflects real uncertainty, not self-protection.
D. Life safety codes do not regulate cost contingencies.
Question 8
A construction estimate is $12,000,000 in today's dollars. The midpoint of construction is 18 months away, and escalation is projected at 4% per year, compounded annually. What is the escalated estimate at the midpoint (rounded to the nearest $1,000)?
A. $12,480,000
B. $12,979,000
C. $12,720,000
D. $12,727,000
Answer: D
ANSWER D. $12,727,000 WHY THIS IS THE BEST ANSWER Escalated cost = $12,000,000 x (1.04)^1.5 = $12,000,000 x 1.06060 = $12,727,153, about $12,727,000. Escalating to the midpoint of construction is a common approach because costs are incurred throughout the construction period. WHY THE OTHER OPTIONS ARE LESS APPROPRIATE
A. This applies only one year of escalation.
B. This applies two full years of escalation.
C. This uses simple interest (4% x 1.5 = 6%) instead of compounding.
Question 9
What is the purpose of an owner's construction contingency in a hospital project budget?
A. To fund the hospital's operating expenses, such as staff overtime, during the construction period
B. To provide additional profit to the contractor for accepting the risks of renovation work
C. To pay for items that were intentionally omitted from the base budget to keep it low
D. To fund unforeseen conditions and approved changes during construction, under defined approval rules
Answer: D
ANSWER D. To fund unforeseen conditions and approved changes during construction, under defined approval rules WHY THIS IS THE BEST ANSWER Renovation of existing hospitals often reveals concealed conditions such as undocumented utilities, asbestos, or structural issues. Contingencies provide funds for these risks and for approved changes. Clear rules for who controls and approves contingency use are essential for cost control. WHY THE OTHER OPTIONS ARE LESS APPROPRIATE
A. Operating expenses are part of the operating budget.
B. Contingency is not a profit allowance.
C. Known items should be included in the budget, not hidden in contingency.
Question 10
A change order includes 120 labor hours at $85 per hour and $6,500 in materials. The contract allows a 15% markup on labor and materials combined. What is the total change order amount?
A. $19,205
B. $20,350
C. $16,700
D. $18,230
Answer: A
Answer A. $19,205 WHY THIS IS THE BEST ANSWER Labor = 120 x $85 = $10,200. Labor + materials = $10,200 + $6,500 = $16,700. Markup = 15% x $16,700 = $2,505. Total = $19,205. Owners should verify quantities, rates, and markups against the contract terms when reviewing change orders. WHY THE OTHER OPTIONS ARE LESS APPROPRIATE
B. This value does not follow from the given figures.
C. This is the cost before the 15% markup.
D. This applies the markup to labor only ($10,200 x 1.15 + $6,500).
Why RealExamCollection is the best choice for ASHE CHC exam preparation
Secure your position in a competitive IT industry
The ASHE CHC certification is a strong way to demonstrate your understanding and ability. Our CHC questions & answers help you prepare for it, so you can secure your current position and move your career forward.
Reviewed by IT professionals
We keep our CHC practice questions up to date, with explanations. The questions and answers on RealExamCollection are reviewed by people with professional experience of ASHE technologies.
One place to prepare
RealExamCollection brings together the material you need for the ASHE CHC exam. Explanations are added to the questions to help you understand the logic behind them and prepare for other ASHE exams.
Updated CHC questions & answers
We update the exam files regularly to add new questions. The date of the latest update is shown at the top of this page.
Free CHC demo before you buy
You can view sample CHC questions on this page before buying, to see the format and pattern of the material.
90 days of free updates
You are eligible for 90 days of free updates after buying the CHC exam. If the file is updated in that time, you can download the latest version from your account.